- As-builts record what changed in the field. Under AIA A201-2017 the contractor keeps the marked set and hands it over as a record of the work as constructed.
- Mark changes as they happen and before concealed work is closed in. Locate buried utilities by survey before backfill.
- Many owners withhold payment, or stop the final inspection, when the marked set is missing or out of date.
- Keep a PDF set and the native CAD files, and store them where facility staff can find them for the life of the building.
What are as-built drawings?
As-built drawings are the project drawings marked up to show what was actually built, as opposed to what was designed. People also call them as-builts, as-built plans, as-built blueprints or construction as-builts; all of these mean the same set. AIA Contract Documents explains why owners want them: "These drawings provide a record of the actual locations of building elements such as ducts, pipes, and conduits, which are typically represented diagrammatically in design documents" (AIA Contract Documents). Diagrammatic means the design shows that a pipe runs from one point to another, not its exact path.
The standard AIA general conditions never use the word as-built, but they create the set. Section 3.11 of A201-2017 says the contractor "shall make available, at the Project site, the Contract Documents, including Change Orders, Construction Change Directives, and other Modifications, in good order and marked currently to indicate field changes and selections made during construction". At the end of the job the set is "delivered to the Architect for submittal to the Owner upon completion of the Work as a record of the Work as constructed" (AIA A201-2017).
As-built documentation is the wider package. One public owner's specification section on project record documents covers "Record Drawings (As-Builts)" and "Record Product Data" together (section 01 78 39). For the full closeout package, see the construction closeout checklist. For how as-builts differ from the finished record set, see record drawings vs as-built drawings.
Who prepares as-built drawings?
The people who did the work mark it up. A typical specification tells the contractor to "Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints" (Alabama State Military Department, section 01 78 39). The electrician marks the electrical sheets, the plumber the plumbing sheets, and the general contractor keeps the whole set together.
Turning the marked prints into a clean set is a separate job, and contracts assign it differently. Under the AIA owner-architect agreement it is optional: section 4.1.1.16 of B101-2017 "allows architects to provide as-constructed record drawings as a supplemental service" (AIA Contract Documents). Brown University has the contractor "take all field changes/adjustments" from every subcontractor and "add these changes accurately to the CAD file(s)" (Brown University). On Los Angeles public works, the final as-built plans are "prepared by the Bureau of Engineering's Construction Manager" (Los Angeles Bureau of Engineering).
| Who | What they do | Where the duty usually comes from |
|---|---|---|
| Installer or subcontractor | Marks its own changes on the record prints as the work goes in | Owner specification, Division 01 |
| General contractor | Keeps one complete marked set on site, current and apart from the working set | AIA A201-2017 section 3.11 |
| Architect or engineer | Compiles the markups into clean record drawings, if hired to | AIA B101-2017 supplemental service 4.1.1.16 |
| Owner's construction manager (some public owners) | Reviews the markups and may draft the final set | Owner procedures, such as Los Angeles |
| Surveyor or measuring firm | Measures an existing building or site when no reliable drawings exist | A separate contract |
For an existing building with no usable drawings, nobody can mark up a set. A measuring firm or surveyor documents the building as it stands; see as-built survey.
What should as-built drawings show?
Anything that differs from the contract drawings, and anything that will be hard to find later. The same specification lists items to mark, including "Depths of foundations below first floor", "Locations and depths of underground utilities", "Revisions to routing of piping and conduits", "Revisions to electrical circuitry", "Actual equipment locations" and "Duct size and routing" (section 01 78 39).
Each change should carry its source. Markups should "Note Construction Change Directive numbers, alternate numbers, Change Order numbers, Addendum number(s), and similar identification" (section 01 78 39). Los Angeles adds "responses to requests for information" and jobsite memos to the changes it wants recorded (Los Angeles Bureau of Engineering). An RFI, or request for information, is the contractor's written question to the designer, and its answer often changes the work.
| Drawing type | What the as-builts must capture | Why it matters later |
|---|---|---|
| Architectural as-built drawings and floor plans | Moved walls and doors, changed finishes, room numbers as tagged in the field | Leasing plans, renovation, life safety plans |
| Electrical as-built drawings | Circuit changes, panel and equipment locations, conduit and duct bank routes, the one-line diagram | Safe shutdowns, added loads, troubleshooting |
| Mechanical and plumbing | Duct sizes and routes, pipe routes, valve and cleanout locations | Maintenance access and fast shutoff |
| Structural | Foundation depths, added steel or openings, embedded items | Future openings, added loads, repairs |
| Civil and site | Location and depth of underground utilities, grades, pavement changes | Digging safely, permits, new connections |
Brown University asks that floor plan changes "include revised room numbers, as physically tagged in the field", and at turnover requires "framed charts in appropriate building MEP rooms for one line diagrams, process flow diagrams and valve charts" (Brown University). A one-line diagram shows how power flows from the service to each panel. For the MEP sheet types themselves, see MEP drawings and RVT files.
When are as-built drawings required?
On most commercial and public projects the contract requires them, and three kinds of document set the rule. The general conditions create the duty (A201-2017 section 3.11, above). The specifications say how: the federal guide specification puts it in "DIVISION 01 - GENERAL REQUIREMENTS SECTION 01 78 00 CLOSEOUT SUBMITTALS" (UFGS 01 78 00), and many owners add a section 01 78 39, Project Record Documents, like the one quoted above. Public agencies add their own manuals.
State transportation departments are the clearest case. "ADOT is required by State law to keep an official record of the final plans for all construction projects which involve ADOT oversight (per Arizona Revised Statues ARS 32-152)" (ADOT Record Drawing Guidelines). Virginia DOT says final as-built plans "will serve as a permanent record of the actual location of all constructed elements of the project", and calls documentation of components, "those visible and more importantly those hidden from view", "a contractual requirement" (VDOT).
Owners enforce it through payment. Brown University warns that "Failure to maintain accurate as-built mark-ups will constitute sufficient justification for withholding payments to the contractor" (Brown University). Los Angeles requires "a signed certification with each monthly payment request" that the record drawings are complete (Los Angeles Bureau of Engineering). Under the Alabama specification, missing record prints at the final inspection "may result in the Owner immediately terminating the Final Inspection" (section 01 78 39).
Small residential jobs often have no written requirement, but an owner can still ask for the marked set in the contract. This page is general information, not legal advice: the contract and the agency rules on your project decide what is required.
How do you make as-built drawings?
Most of the work is discipline during the job, not drafting at the end. A routine that works:
- Keep one dedicated set. "Do not use Project Record Documents for construction purposes" (section 01 78 39): the record set stays clean and in the site office.
- Mark changes the day they happen. The same specification says: "Post changes and modifications to Project Record Documents as they occur; do not wait until the end of the project."
- Record hidden work before it is covered: "Record and check the markup before enclosing concealed installations." For buried pipes and duct banks, Los Angeles wants them "precisely located by survey and recorded on the As Built Drawings before backfilling" (Los Angeles Bureau of Engineering).
- Use a color code and words. One specification says "Mark record sets with erasable, red-colored pencil"; the federal one uses red for deletions, green for additions and blue for special notes, and asks for written explanations next to the marks (UFGS 01 78 00). Record drawings vs as-built drawings covers redline conventions in detail.
- Cite the source of every change: change order, RFI, bulletin or addendum number. Keep the change order and RFI logs and the submittal log in step with the drawings.
- Review the set with the owner at each pay application, then transfer the markups into the CAD files at closeout.
As-built drawings example: a clinic fit-out (illustrative)
An illustrative markup log for a fictional one-floor clinic fit-out, as it might look when the marked set is handed over. Sheet numbers, change numbers and dimensions are invented for this page.
| Sheet | Markup on the as-built set | Source of the change | Color |
|---|---|---|---|
| A-101 Floor plan | Exam room 104 wall moved 18 inches east; door swing reversed; room numbers updated to match field signs | RFI 012 answer | Red deletion, green addition |
| E-201 Power plan | Two receptacles added on circuit 14; circuit 9 split into circuits 9 and 11 | Change order 03 | Green addition |
| E-601 One-line diagram | Feeder to panel LP-2 updated to the size installed | Approved submittal | Blue note |
| M-201 HVAC plan | Supply duct rerouted above the corridor to clear a beam; size changed to fit | RFI 019 and field coordination | Red and green, with a note |
| P-101 Plumbing plan | Sanitary line depth recorded at four points before the slab pour | Field measurement | Green, with dimensions |
| C-101 Site utilities | Water service located by survey before backfill, 3 feet north of the design line | Survey shots, field memo 07 | Green, with survey point numbers |
The clean record set later folds these changes into the drawings and drops the colors. The marked set and the logs are what show why each change was made.
How much do as-built drawings cost?
There is no standard price, because two different jobs share the name. Marking up drawings during construction is part of the contractor's work and is normally carried in its contract price. Preparing as-built drawings of an existing building, where nobody has a current set, is a separate service: a firm measures the building and drafts floor plans, elevations or a model. Firms that offer as-built drawing services price that measuring and drafting. What drives the cost:
- Floor area, number of levels and the number of rooms and spaces to measure.
- What has to be shown: floor plans only, or also elevations, sections, ceiling plans and MEP systems.
- Required accuracy, which decides between tape and laser measurements and laser scanning (see as-built survey).
- The deliverable: PDF drawings, editable CAD files or a BIM model.
- Access: occupied spaces, after-hours work, locked rooms and ceiling access.
- Concealed conditions: nothing behind walls or under slabs can be drawn accurately without opening or locating it.
Federal work shows how far the scope can go: GSA's 2024 P100 submittal matrix lists "Reality Capture documentation (for an existing building, or historic site, and if required by scope) - e.g. Laser Scans, existing conditions model, 360 photos, etc." (GSA P100 submittal matrix). Ask for quotes on the same written scope so they can be compared.
How should you store as-built drawings, and for how long?
Keep two forms: a PDF set anyone can open, and the native CAD or BIM files someone can edit. For long-term records, the National Archives lists "Portable Document Format/Engineering (PDF/E)" as an acceptable format for CAD records, with STEP and the ASTM E57 3D file format among its preferred ones (National Archives). Name files so the as-built version is obvious: Virginia DOT adds "ab" to the sheet number, so "plan sheet number 03 would be renamed 03ab" (VDOT).
How long depends on the owner and the asset. Arizona's transportation department aims "to maintain the engineering records for all civil construction projects for decades to come" (ADOT). Cornell University holds closeout project material "for 8 years after the close of contract" and indexes drawings by type, with codes such as "A = As-built", "R = Record" and "E = Existing Conditions" (Cornell Facilities and Campus Services). For a building you own, keep the drawings for as long as you own it and hand them to the next owner.
Limit access where drawings are sensitive. Arizona keeps record drawings of critical structures off its public portal: "Access to the record drawings for critical structures must be requested through the ADOT Office of Safety & Risk Management" (ADOT).
Common mistakes with as-built drawings
Most bad as-builts come from leaving the work to the end of the job.
- Rebuilding the markups from memory at closeout instead of marking changes as they happen.
- Closing walls, ceilings or trenches before the location of what is inside is recorded.
- Marking the working set used on site, so it ends up torn, stained and full of crossed-out options.
- Showing a change without the change order, RFI or bulletin number behind it.
- Updating a plan but not the schedules, details and one-line diagram that depend on it.
- Treating diagrammatic runs as exact. Measure or survey anything someone may later dig or drill near.
- Handing over PDFs only, so the next design team has to redraw the building.
Are as-built drawings also a data asset?
They can be, as part of a firm's full project archive. AI data buyers have asked Origin for CAD files and drawing sets from architecture, engineering and construction firms, with years of revision history, and for the project records around them (RFIs, submittals, change orders). The value is in the revision trail: design intent, each change and what was built. As-built drawings are the last step of that trail, so a marked set kept with its RFI and change order logs says more than the clean drawings alone.
What must come out first: client-confidential and security-sensitive drawings, personal data in title blocks and correspondence, and anything the firm does not own under its contracts. Who owns drawings is set by the design contract, not by who holds the files: see who owns architectural drawings, the ITAR and EAR checklist for CAD files and de-identifying company data.
Origin is an independent data partner. Your firm decides what is shared and signs any license itself, and a buyer may pay Origin when a deal closes.
Does your company hold records like these? See what your data is worth.
Common questions
What is the purpose of as-built drawings?
As-built drawings show where things really are after construction: walls, doors, pipes, ducts, conduit, equipment and buried utilities. Facility staff use them to maintain and repair the building, designers use them as the starting point for renovations, and owners use them for permits, insurance and sale. Without them, every later project starts by measuring and opening walls.
Who is responsible for as-built drawings on a construction project?
The contractor keeps the marked-up set during construction and hands it over at closeout; under AIA A201-2017 section 3.11 it must keep the contract documents marked currently to show field changes. Each subcontractor usually marks its own work. Turning the markups into clean record drawings is a separate task that the contract gives to the architect, the contractor or the owner.
Are as-builts the same thing as record drawings?
Not quite. As-builts are usually the contractor's marked-up field set; record drawings are the clean, complete set compiled from those markups at closeout. The AIA calls the compiled set as-constructed record drawings and notes they are commonly called as-builts, so people use the words loosely. Some owners even swap them, so read the definitions in your contract.
What should electrical as-built drawings include?
Electrical as-builts should show circuit changes, the actual locations of panels and equipment, conduit and duct bank routes, and a one-line diagram that matches what was installed. Buried conduit and duct banks should be located by survey before backfill. Panel schedules should match the breakers actually installed, so electricians can isolate circuits safely later.
How do I get as-built drawings for an existing building?
Start with the people who built or approved it: your own files, the original architect or contractor, and the local building department, which may hold permit drawings. Permit drawings show the design, not later changes, so check them on site. If nothing usable exists, hire a measuring firm or surveyor to document the building as it stands.
What drives the cost of as-built drawings for an existing building?
Mainly the size of the building, how much has to be shown (floor plans only, or also elevations, ceilings and MEP systems), the accuracy required, the deliverable (PDF, CAD or a BIM model) and access to occupied or locked spaces. Concealed conditions add cost, because walls and slabs must be opened or scanned. Compare quotes on one written scope.
How long should as-built drawings be kept?
For the life of the building. Owners keep them as long as they own the asset and pass them to the next owner; Arizona's transportation department plans to maintain its engineering records for decades. Store a PDF set for reading and the native CAD or BIM files for editing, and keep a second copy somewhere other than the building.
What is the difference between as-built drawings and shop drawings?
Shop drawings are made before installation by a trade contractor or fabricator to show exactly how its work will be built, and they go through submittal review. As-built drawings are made during and after installation to show what was actually built. Approved shop drawings often feed the as-builts, and some specifications let the contractor mark them instead of the contract drawings.
Sources and further reading
- AIA Document A201-2017, General Conditions of the Contract for Construction (sample)
- AIA Contract Documents: How AIA Contract Documents Address As-Built Drawings
- Alabama State Military Department: Section 01 78 39, Project Record Documents
- Brown University Facilities: Section 01 17 71, Project Turnover Requirements
- City of Los Angeles, Bureau of Engineering: 25.2 Record Drawings and As-Built Plans
- WBDG: UFGS 01 78 00, Closeout Submittals
- Arizona Department of Transportation: Record Drawing Guidelines
- Virginia Department of Transportation: Guidelines for As-Built Documentation (2024)
- National Archives: Appendix A, Tables of File Formats
- Cornell Facilities and Campus Services: Drawing Type Definitions
- GSA: 2024 P100 Submittal Matrix