- An as-built survey compares what was built with what was approved, in real coordinates and elevations.
- Where a city or title insurer relies on it, a licensed surveyor prepares and certifies it.
- Accuracy is specified, not assumed: tolerances for site work, and USIBD levels of accuracy (LOA10 to LOA50) for building scans.
- Cost depends on scope, accuracy, timing, access and deliverables. Get quotes on one written scope.
What is an as-built survey?
An as-built survey records where constructed work actually sits, in measured coordinates and elevations. The City of Orlando uses the definition in Florida's surveying rules: "a survey performed to obtain horizontal and/or vertical dimensional data so that constructed improvements may be located and delineated" (City of Orlando). Improvements here means anything built on the land: buildings, pipes, structures, pavement, curbs and ponds.
It is not the same as as-built drawings. As-built drawings are the contractor's markups of the design drawings; an as-built survey is a measurement, usually by a surveyor, and is often used to check those markups. It also differs from the other common surveys:
| Survey | Main question it answers | When |
|---|---|---|
| Construction layout (staking) | Where should this be built? | Before and during construction |
| As-built survey | Where was it actually built, and does it match the plans? | During construction for buried work, and at completion |
| Boundary survey | Where are the property lines and corners? | Purchase, financing, design |
| ALTA/NSPS land title survey | What does a title insurer need to know about the land and its improvements? | Commercial purchase or refinancing |
| Existing conditions survey or building scan | What is in this building or on this site now? | Before renovation or design |
What does an as-built survey include?
Local rules set the content, and Orlando's checklist is a good model because it is specific. The survey data "must be overlaid on the construction plan set that was approved for your project", with plan information in grayscale and as-built information in bold, and shots "taken at the same locations as shown on the plans for ease of comparison" (Orlando as-built survey checklist).
The minimum items start with "Storm and sanitary sewers and structures (including cleanouts), drainage conveyance systems and retention ponds" and water mains, and run through meters, valves, gas mains, irrigation lines, process piping, "Electric and communication duct banks", signals, transformers, fences, pavement, curbs, sidewalks, driveways and buildings (Orlando checklist).
| Element | What the survey records | Why it matters |
|---|---|---|
| Storm and sanitary pipes and structures | Location, rim and invert elevations, pipe size and material | Gravity lines only work if the slopes match the design |
| Water, gas and reclaimed water lines | Location and depth of mains, valves, meters and cleanouts | Future connections and safe digging |
| Electric and communication duct banks | Route, depth, pull boxes, transformers and cabinets | Finding and expanding service later |
| Grading and ponds | Finished grades, pond bottoms and banks | Stormwater storage and permit compliance |
| Pavement, curbs, sidewalks and driveways | Edges, elevations and flow lines at grade breaks | Drainage, accessibility and acceptance |
| Buildings and structures | Footprint, position and finished floor elevation | Setback and elevation checks |
Coordinates and elevations must tie to a known system. Orlando requires "Florida State Plane Coordinates" and elevations "in North American Vertical Datum (NAVD) of 1988", tied to published control. The certification "must qualify the purpose of the survey, horizontal and vertical datums and the last date in the field", and the CAD files "must be identically matching to the signed and sealed as-built survey" (Orlando checklist).
Who can prepare an as-built survey, and how accurate must it be?
When an agency, lender or title insurer will rely on the survey, a licensed land surveyor prepares and certifies it. Orlando's rule is typical: "The as-built survey must be prepared by a Florida Licensed Professional Surveyor and Mapper", and "The Surveyor's Certification must be included in the survey" (Orlando checklist). Contractors may collect their own measurements during the work, but the agency reviews the certified survey: Orlando's Survey Section is "responsible for reviewing, rejecting and accepting" as-built surveys for private and public projects (City of Orlando).
Accuracy is set by the reviewing agency or the contract. Orlando requires constructed public storm and sanitary sewer improvements, and those connected to the public system, to be within 0.5 feet horizontally and 0.2 feet vertically of the location shown on the construction plans (Orlando checklist). Ask for the tolerance in writing before the survey starts, so the surveyor picks methods that can prove it.
Licensing rules differ from state to state. This page is general information, not legal advice: check with your state surveying board and with the agency that will review the survey.
Is an ALTA/NSPS survey the same as an as-built survey?
No, though they overlap. An ALTA/NSPS Land Title Survey follows national standards that "the ALTA and the NSPS jointly promulgate", written because title insurers "have specific needs, unique to title insurance matters" (2026 ALTA/NSPS standards). The current standards are effective February 23, 2026. The survey shows "The location of buildings on the surveyed property" and "the character and location of all walls, buildings, fences, and other improvements within five feet of each side of the boundary lines", measured against the boundary.
An as-built survey measures improvements against the design instead. The buyer or lender of a newly finished building may order both, or one ALTA/NSPS survey with optional items: the request names "which of the optional items listed in Table A, if any, are to be incorporated", such as "Measured height of all buildings above grade at a location specified by the client" (2026 ALTA/NSPS standards).
| As-built survey | ALTA/NSPS land title survey | |
|---|---|---|
| Purpose | Confirm construction matches the approved plans | Support title insurance and lending |
| Compared against | The approved design drawings | The boundary, easements and record documents |
| Standard | Agency or contract requirements, such as a city checklist | National ALTA/NSPS standards, effective February 23, 2026 |
| Usual client | Contractor, developer or owner, for agency acceptance | Buyer, lender or title insurer |
| Accuracy measure | Tolerances set by the agency or contract | Relative Positional Precision of the boundary corners |
On the ALTA/NSPS side, the standards call Relative Positional Precision "the accepted indicator of measurement quality on an ALTA/NSPS Land Title Survey" (2026 ALTA/NSPS standards).
What drives as-built survey cost?
There is no standard as-built survey cost, because the scope runs from one house foundation to miles of utilities. Quotes are built from field time and office time, and these are the main drivers:
- Number and type of features: every pipe, structure, valve and grade break is another measurement.
- Required accuracy: tighter tolerances need better control and more checks.
- Timing: buried work has to be measured before backfill, which means repeat visits during construction rather than one visit at the end.
- Control and datums: tying into state plane coordinates and published benchmarks, and replacing control lost during the work. Orlando requires the surveyor to "reference and replace any project control points, boundary corners, benchmarks, section corners and any other control monuments that may be lost or destroyed during construction" (Orlando checklist).
- Deliverables: an overlay on the approved plans, CAD files in the format and layers the agency requires (Orlando wants storm features on layers "beginning with V-STRM"), and signed PDFs.
- Access and safety: traffic control, confined spaces, occupied buildings and night work.
- Resubmittals: a survey the agency rejects comes back for another round.
For a building interior, cost follows floor area, the level of accuracy and the deliverable: a registered point cloud alone, 2D floor plans, or a full BIM model. Ask for quotes on one written scope that names the features, the tolerance or level of accuracy, the datum and the file formats.
How accurate is a laser scan? USIBD levels of accuracy
For buildings, accuracy is usually specified with the Level of Accuracy (LOA) specification of the U.S. Institute of Building Documentation (USIBD). Its guide says "The five defined Levels of Accuracy are - LOA10, LOA20, LOA30, LOA40 and LOA50", each "Specified at the 95 percent confidence level" (USIBD LOA guide, version 2.0). The ranges below are from that version 2.0 guide. The current specification is version 3.1, which "introduces a dedicated section on how to specify tolerances using standard deviation" (USIBD).
| Level | Upper end of the range | Lower end of the range |
|---|---|---|
| LOA10 | User defined | 5 cm |
| LOA20 | 5 cm | 15 mm |
| LOA30 | 15 mm | 5 mm |
| LOA40 | 5 mm | 1 mm |
| LOA50 | 1 mm | 0 |
Two details matter when you write the scope. Levels can differ by element: the guide says the LOA "may be applied to the elements of the building documentation project and not necessarily to the project in totality", so structure can be held to a tighter level than finishes. And a model cannot be more accurate than the scan behind it: "The represented accuracy can only be even or less accurate than the measured accuracy" (USIBD LOA guide).
What is scan to BIM (point cloud to BIM)?
Scan to BIM means modeling a building in BIM software from a laser scan. BIM, building information modeling, is a 3D model whose parts carry data, such as a wall's type or a pipe's size. Autodesk's Revit help describes the starting point: "You can use point clouds to provide the existing condition of a building or site" (Revit help). A point cloud is the set of measured points the scanner records.
The usual steps:
- Scan from several positions. "Typically, multiple locations of a building are individually scanned and registered together, resulting in a highly accurate 3D point cloud of a region or of the entire building" (Revit help). Registering means joining the scans in one coordinate system.
- Process the data. Autodesk ReCap is used "to convert scan file data (raw format) to a point cloud format that can be viewed and edited in other products"; in Revit, "An .rcp format file is a project file that groups together multiple .rcs scan files" (Revit help, insert a point cloud).
- Link, do not embed. Scans are "typically huge (hundreds of millions to billions of points)", so Revit "links a point cloud as a reference rather than embedding the file" (Revit help).
- Model to the agreed level of accuracy and detail, element by element, and check the model against the cloud.
- Deliver the model and the registered point cloud in an open format too. ASTM E2807 defines the E57 format, which stores "3D point data", color and intensity values and the scanner's photographs (ASTM E2807); the National Archives lists E57 among its preferred formats for long-term CAD records (National Archives).
The result is often called an as-built model or existing conditions model. Federal construction specifications define a record model as "A model reflecting approved changes during construction including red-lines, requests for information (RFI's), and contract modifications" (UFGS 01 78 00), and GSA asks for "Laser Scans, existing conditions model, 360 photos" on existing buildings where the scope requires them (GSA P100 submittal matrix).
Example: as-built survey check on a small site (illustrative)
An illustrative comparison from a fictional as-built survey of a small commercial site, checked against tolerances like Orlando's for storm and sanitary work (0.5 feet horizontal, 0.2 feet vertical). All values are invented for this page.
| Feature | Design | As-built | Difference | Within tolerance? |
|---|---|---|---|---|
| Storm structure S-3, rim elevation | 101.20 ft | 101.27 ft | +0.07 ft | Yes |
| Storm pipe S-3 to S-2, downstream invert | 96.40 ft | 96.66 ft | +0.26 ft | No (vertical) |
| Storm pipe S-2 to S-1, upstream invert | 96.10 ft | 96.02 ft | -0.08 ft | Yes |
| Sanitary manhole MH-1, position | Plan location | 0.3 ft east | 0.3 ft | Yes |
| Sanitary cleanout CO-2, position | Plan location | 0.8 ft north | 0.8 ft | No (horizontal) |
| Building finished floor | 102.50 ft | 102.48 ft | -0.02 ft | Yes |
Two items fall outside tolerance. The surveyor reports them as measured; the engineer and contractor then decide whether to fix the work or document an accepted change before the agency reviews the survey.
Common mistakes when ordering an as-built survey
Most failed as-built surveys fail on timing or on a missing requirement, not on the measuring.
- Calling the surveyor after backfill, when buried pipes and duct banks can no longer be measured.
- No written tolerance or level of accuracy, so nobody can say whether the survey passes.
- Using an assumed datum where the agency requires state plane coordinates and NAVD 88; Orlando publishes a "Memo on Assumed Datum for As-built Surveys" (City of Orlando).
- Losing survey control during construction and not replacing it.
- Ordering a point cloud without saying what model or drawings must come out of it.
- Assuming an ALTA/NSPS survey also checks the work against the approved plans.
- CAD files that do not match the signed survey, or that use the wrong layers.
Are as-built surveys and scans also a data asset?
Mostly as part of the project record they close. AI data buyers have asked Origin for CAD files and drawing sets from architecture, engineering and construction firms, with years of revision history, and for the project records around them (RFIs, submittals, change orders). The value is in the revision trail: design intent, each change and what was built. An as-built survey is the measured end of that trail: it shows what was built against the approved design, next to the drawings and change records that explain the differences.
What must come out first: client-confidential and security-sensitive drawings, personal data in title blocks and correspondence, and anything the firm does not own under its contracts. Surveying firms whose own archive is scans and LiDAR rather than design files should read licensing aerial imagery, LiDAR and 3D data; design firms should start with who owns architectural drawings.
Origin is an independent data partner. Your firm decides what is shared and signs any license itself, and a buyer may pay Origin when a deal closes.
Does your company hold records like these? See what your data is worth.
Common questions
What is the difference between an as-built survey and a boundary survey?
A boundary survey locates the property lines and corners of a parcel. An as-built survey locates what was constructed, such as buildings, pipes, structures, pavement and grades, and usually compares it with the approved plans. One answers where the land ends; the other answers where the work actually is. Some projects need both.
Who can prepare an as-built survey?
When a city, lender or title insurer relies on it, a licensed professional land surveyor prepares and certifies it. Orlando, for example, requires a Florida licensed surveyor and mapper and a certification stating the purpose, the datums and the last date in the field. Contractors may collect their own measurements during the work, but agencies review the certified survey.
How much does an as-built survey cost?
It depends on scope, so ask for quotes on a written scope rather than a rate. Cost rises with the number of features to measure, tighter tolerances, repeat visits to measure buried work before backfill, tying into state plane coordinates and benchmarks, traffic control or confined spaces, and the CAD and PDF deliverables the reviewing agency requires.
What is scan to BIM?
Scan to BIM is the process of building a BIM model of an existing building from a laser scan. The scanner captures measured points from several positions, the scans are registered into one point cloud, and a modeler then draws walls, floors, structure and systems in software such as Revit, checking the model against the cloud to an agreed level of accuracy.
What file format should a point cloud be delivered in?
Ask for an open format as well as the working files. ASTM E2807 defines the E57 format, which stores 3D points, color, intensity and the scanner's photographs, and the National Archives lists E57 among its preferred formats for long-term records. Revit users also work with indexed .rcp and .rcs files created in Autodesk ReCap.
What does LOA mean in laser scanning?
LOA means level of accuracy, from the U.S. Institute of Building Documentation specification. It has five levels, LOA10 to LOA50, each a range at 95 percent confidence; in the version 2.0 guide, LOA30 runs from 15 mm down to 5 mm. Different elements of one project can be specified at different levels.
When is an as-built survey required?
Usually when an agency accepts or permits the work: cities require as-built surveys of storm and sanitary sewers, water mains, duct banks, pavement and other improvements before accepting them, as Orlando does. Buyers and lenders may ask for a survey when a building is finished, and owners order building scans before renovating. Your permit and contract say which applies.
What is an as-built model?
An as-built model is a BIM model that shows a building as constructed rather than as designed. It is made either by updating the design model with red-lines, RFI answers and contract changes during construction, which federal specifications call a record model, or by modeling an existing building from a laser scan. Either way, it should state its accuracy.
Sources and further reading
- City of Orlando: As-Built Surveys
- City of Orlando: As-Built Survey Checklist (2026)
- ALTA and NSPS: 2026 Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys
- USIBD Level of Accuracy (LOA) Specification Guide, Document C120, version 2.0 (2016)
- USIBD: Level of Accuracy (LOA) Specification
- Autodesk Revit help: About Point Clouds
- Autodesk Revit help: Insert a Point Cloud File
- ASTM E2807: Standard Specification for 3D Imaging Data Exchange (E57)
- National Archives: Appendix A, Tables of File Formats
- WBDG: UFGS 01 78 00, Closeout Submittals
- GSA: 2024 P100 Submittal Matrix