Project Closeout Checklist: Construction Closeout Documents

A construction closeout checklist with every document the owner expects: as-builts, O&M manuals, warranties, lien waivers and the final pay app. Free Excel.

Starts at
Substantial completionthe punch list and Certificate of Substantial Completion
Ends at
Final paymentand release of remaining retainage
Download
Closeout checklist (CSV)opens in Excel or Google Sheets
Rolled drawings, a hard hat and a tape measure in a site office
Short answer

Construction project closeout is the set of steps between substantial completion and final payment: the punch list, the Certificate of Substantial Completion, the record documents (as-builts, approved submittals, change orders), O&M manuals, warranties, spare parts, and the financial package (final pay application, lien waivers, insurance and surety documents). Under AIA A201-2017, final payment and the remaining retainage are not due until the contractor delivers that package. Use the free checklist below to track each document, who provides it and when.

  • Closeout starts when the contractor asks for a substantial completion inspection, not after the last trade leaves.
  • Under A201-2017, warranties usually start on the date of substantial completion.
  • Final payment and remaining retainage wait for the affidavit of payment, insurance and surety documents, warranties and any lien waivers the owner asks for.
  • Keep your own closeout set too: the final job cost against the estimate is the record your next bid needs.

What is project closeout in construction, and when does it start?

Closeout is the handover of a finished building and the paperwork that proves it was built as agreed and paid for. It starts at substantial completion, which A201-2017 defines as the stage when the work is "sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use" (AIA A201-2017, 9.8.1). It ends with final payment.

Good closeout starts long before that date. Record drawings, warranties and O&M manuals are collected from subcontractors and suppliers during the job, so the last month is spent checking documents, not chasing them.

Clause numbers on this page refer to AIA A201-2017, the most widely used general conditions. Your contract may use a different form or amend these clauses: follow the contract you signed. This page is general information, not legal advice.

The closeout documents list: what, who provides it and when

Most closeout packages contain the documents below. Your specifications list the exact items, usually in a closeout section; on federal work that is Unified Facilities Guide Specification 01 78 00, "Closeout Submittals" (WBDG). Download the construction closeout checklist (CSV) to track each one.

DocumentWho provides itWhenWhere the requirement comes from
List of items to be completed or corrected (punch list)ContractorWhen requesting the substantial completion inspectionA201-2017 9.8.2
Certificate of Substantial Completion (for example AIA G704)Architect prepares; owner and contractor signAt substantial completionA201-2017 9.8.4 and 9.8.5
Record set: contract documents, change orders and other modifications marked with field changes, plus approved submittalsContractorOn completion of the workA201-2017 3.11
As-built and record drawingsContractor (record drawings by contractor or designer, per contract)Per specificationsCloseout specification section
Operation and maintenance (O&M) manualsContractor, from manufacturers and subcontractorsPer specifications, usually before training and handoverCloseout specification section
Spare parts and extra stockContractorPer specificationsCloseout specification section
Special warranties (manufacturer and subcontractor)ContractorBefore final paymentA201-2017 9.10.2
Affidavit of payment, insurance certificate, consent of surety, lien releases and waiversContractor, subcontractors, suretyBefore final paymentA201-2017 9.10.2
Final application for payment (for example AIA G702 with G703)ContractorWith the notice that work is ready for final inspectionA201-2017 9.10.1

Substantial completion and the punch list

When the contractor considers the work substantially complete, it "shall prepare and submit to the Architect a comprehensive list of items to be completed or corrected prior to final payment" (AIA A201-2017, 9.8.2). The architect inspects and, if the work passes, prepares the Certificate of Substantial Completion. The AIA G704 form attaches the list: "A list of items to be completed or corrected is attached hereto" (AIA G704-2017).

Three things change on that date. The certificate fixes the time to finish the punch list and splits responsibility for security, utilities, damage and insurance. "Warranties required by the Contract Documents shall commence on the date of Substantial Completion" unless the certificate says otherwise (AIA A201-2017, 9.8.4). And once the owner and contractor accept the certificate, and the surety consents if there is one, "the Owner shall make payment of retainage applying to the Work or designated portion thereof", adjusted for incomplete work (AIA A201-2017, 9.8.5).

Financial closeout: final pay application, retainage and lien waivers

Final payment starts with the contractor's notice that the work is ready and "a final Application for Payment" (AIA A201-2017, 9.10.1). On AIA forms that is the G702, Application and Certificate for Payment, which carries the net change by change orders and the retainage (AIA G702), with the G703 continuation sheet listing each line of the schedule of values (AIA G703).

A201-2017 9.10.2 then says: "Neither final payment nor any remaining retained percentage shall become due until the Contractor submits to the Architect" six items (AIA A201-2017):

  • an affidavit that payrolls, bills for materials and equipment and other debts connected with the work have been paid or satisfied;
  • a certificate that insurance required to stay in force after final payment is in effect;
  • a written statement that the contractor knows of no reason the insurance will not be renewable;
  • consent of surety to final payment, if there is a surety;
  • documentation of special warranties, such as manufacturers' warranties or specific subcontractor warranties;
  • if the owner requires it, other proof of payment, "such as receipts and releases and waivers of liens".

As-built drawings, record drawings and O&M manuals

During the job, A201-2017 requires the contractor to keep at the site the contract documents, "including Change Orders, Construction Change Directives, and other Modifications, in good order and marked currently to indicate field changes", plus the approved submittals. On completion they are "delivered to the Architect for submittal to the Owner upon completion of the Work as a record of the Work as constructed" (AIA A201-2017, 3.11).

Federal specifications draw a useful line between two terms. "As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the Contract Documents", including deviations from "official responses to submitted Requests for Information". "The record drawings are the final compilation of actual conditions reflected in the as-built drawings." (UFGS 01 78 00).

O&M manuals collect what the owner's facility staff need to run the building: equipment data, maintenance schedules, wiring and control diagrams, and the contacts for warranty service. Assemble them by system, in the order of the specification sections, and include the start-up and test reports for each piece of equipment.

Warranties, spare parts and attic stock

Collect warranties as each trade finishes, not at the end. Each warranty should name the product, the installer, the start date and the end date, and say who to call. Federal closeout specifications go further and require a "Warranty Management Plan" and "Spare Parts Data" (UFGS 01 78 00).

Extra stock, often called attic stock (spare tile, carpet, paint, ceiling panels), is handed over with a signed transmittal listing each item and quantity. Without the transmittal, the owner cannot prove it was received.

Example: closeout log for a mid-size project (illustrative)

An illustrative closeout log two weeks after substantial completion on a fictional three-storey office building. Names and dates are invented.

DocumentStatusNote
Certificate of Substantial CompletionSigned by owner and contractor on 1 MarchPunch list of 212 items attached; 30 days to finish
Punch list168 of 212 items closedRoofing and door hardware items open
Record set with field changesReceivedMarked drawings, 41 change orders, approved submittals
As-built drawingsUnder reviewMEP sheets missing two RFI changes
O&M manuals9 of 11 systems receivedFire alarm and elevator outstanding
Special warranties14 of 16 receivedRoofing manufacturer warranty pending final inspection
Attic stockDelivered with transmittalSigned by building engineer
Lien waivers22 of 25 subcontractorsThree final waivers outstanding
Final application for paymentNot yet submittedWaiting on the items above

Common closeout mistakes

Most closeout delays come from documents that were never requested during the job.

  • Starting closeout after the last trade leaves. Ask for warranties, O&M data and as-builts when each subcontract is about two-thirds done.
  • As-builts that miss RFI answers and field changes. Update the marked set weekly, not from memory at the end.
  • Warranty dates that do not match the Certificate of Substantial Completion. Under A201-2017 they start on that date unless the certificate says otherwise.
  • Final lien waivers collected before the last payment to the subcontractor clears.
  • Closing open change orders and potential change orders in a rush. Settle them before the final pay application, or the dispute outlives the job.
  • No internal closeout. The owner gets the record set; your company should keep its own final job cost, logs and lessons learned.

How long to keep closeout records

There is no single number. Retention depends on the contract (public and federal contracts often set their own record periods), the warranty periods, tax rules and the time limits for construction defect claims, which differ from state to state. Ask your counsel for the periods that apply where you build, and set the longest one as your default.

Keep the full project, not just the final documents: the RFI, submittal and change order logs, daily logs and the cost report show how the job was actually built, which a final drawing set cannot.

Your closed projects are also a data asset

Years of closed projects, each with an estimate, the final cost, and the RFIs, submittals and change orders in between, are records AI developers building estimating and project-management tools ask for. A contractor can describe its own records without sending any files; drawings owned by architects or owners, and personal data, stay out. See selling construction project records to AI companies and the construction contractor data guide.

If your company keeps years of closed project records, the guide for construction contractors explains what AI developers ask for and who signs. To see what yours could be worth, describe them in six questions; no files or system access needed.

Common questions

What documents are in a construction closeout package?

Usually the punch list and Certificate of Substantial Completion, the record set with field changes and approved submittals, as-built drawings, O&M manuals, warranties, spare parts and attic stock, and the financial documents: final pay application, affidavit of payment, insurance and surety documents, and lien waivers if the owner requires them.

When does construction closeout start on a typical project?

Formally at substantial completion, when the contractor submits its list of items to complete or correct and the architect inspects. In practice, collecting warranties, O&M data and as-builts should start when each trade is well into its work.

Who signs the Certificate of Substantial Completion under AIA contracts?

Under A201-2017 the architect prepares it, and it is submitted to the owner and contractor for their written acceptance of the responsibilities it assigns. The AIA G704 form has signature lines for the architect, contractor and owner.

When is retainage released at the end of a construction project?

Under A201-2017, retainage for the completed work is paid after the owner and contractor accept the Certificate of Substantial Completion and the surety consents, adjusted for incomplete work. Any remaining retainage is due with final payment, after the contractor submits the documents listed in section 9.10.2.

What is the difference between as-built drawings and record drawings?

In the federal closeout specification, as-built drawings are the marked-up drawings the contractor keeps on site showing actual conditions and deviations, and record drawings are the final compilation of those conditions. Many contracts use the two terms loosely, so check the definitions in yours.

How long should a construction contractor keep project closeout records?

It depends on the contract, warranty periods, tax rules and the state's time limits for construction defect claims. There is no single national number. Ask your counsel which periods apply and keep complete project records for the longest of them.

Do lien waivers have to be collected before final payment?

Under A201-2017, only if the owner requires them: section 9.10.2 lists releases and waivers of liens among the documents the owner may require before final payment. Many owners and lenders do require them.

What is a project closeout checklist?

A list of every closeout step and document with who provides it and when: punch list, Certificate of Substantial Completion, as-built and record drawings, O&M manuals, warranties, spare parts, final pay application, lien waivers and consent of surety. The project manager tracks it from substantial completion to final payment.

What should a project closeout report cover, and who is it for?

Write it for two readers: your own estimators and managers, and the owner if the contract asks for one. A useful report compares the final cost with the estimate and the schedule of values, lists the change orders and RFIs that explain the difference, records how long submittals took to review, and notes warranty start dates and any open items. It is not the closeout package; that is the set of documents the owner receives, listed in the checklist above.

Sources and further reading