- Redlines are the field markups; record drawings fold them into a clean, complete set.
- AIA, Cornell and the federal guide specification use the terms in that order. Los Angeles uses them the other way round, and Arizona dropped "as-built" in 2015.
- Record drawings are often not sealed as a new design. Owners mark them as record drawings and add a statement of how they were prepared.
- Accuracy rests on the contractor's markups, so locate buried work before anyone digs near it.
What is the difference between record drawings and as-built drawings?
In the most common usage, as-built drawings are the field markups and record drawings are the finished set made from them. Cornell University's facilities office defines as-builts as "Drawings marked up in the field to reflect changes to the design documents" and record drawings as "A complete set of clean drawings that reflect how the project was built - folding the as-built revisions into the design documents, including addenda, post bid bulletins and design revisions" (Cornell Facilities and Campus Services).
Cornell adds the point that matters most for anyone using them later. Record drawings are "not confirmed in the field by the designer", so they are "a compiled record", not a new survey. They "are expected to represent a complete drawing set, not just the sheets that changed" (Cornell).
| As-built drawings (redlines) | Record drawings | |
|---|---|---|
| Made by | The contractor and its trades, in the field | Usually the architect or engineer; sometimes the contractor or the owner |
| When | Throughout construction | At closeout, from the final markups |
| What they look like | Contract prints with colored markups and notes | Clean drawings with the changes drafted in, marked as record drawings and dated |
| Coverage | The sheets where something changed | The complete set, changed or not |
| Checked in the field by the designer? | No; recorded by the people who built it | No; compiled from the markups and change documents |
| Main use | Raw evidence of what changed and why | The owner's long-term reference set |
How does the AIA define record drawings?
The AIA owner-architect agreement, B101-2017, names three related sets among its optional services, and its instructions define each one (AIA B101-2017 instructions):
- Conformed documents for construction, commonly called issued for construction documents: "the Construction Documents modified to include any addenda issued during the bidding or negotiation process and accepted alternates".
- As-designed record drawings: "the record of everything the Architect designed for the Project", including addenda, supplemental instructions, change orders, change directives and minor changes in the work.
- As-constructed record drawings, which the AIA notes are commonly called as-builts: "the record of the Project as constructed based on information the Contractor provides to the Owner under the contract for construction".
None of these is a basic service. Section 4.1.1.16 "allows architects to provide as-constructed record drawings as a supplemental service" (AIA Contract Documents), so the owner has to select it. Some public owners write it into their own edition: South Carolina's state version of B101 says "The Architect shall prepare and provide to the Owner a set of reproducible As-Constructed Record Plans showing all significant changes in the work made during construction" (South Carolina Office of State Engineer).
The contractor's side sits in the general conditions. A201-2017 section 3.11 has the contractor keep the contract documents "marked currently to indicate field changes" and deliver them "as a record of the Work as constructed" (AIA A201-2017). For the full closeout package, see the construction closeout checklist.
One joint committee of the Pittsburgh chapter of the AIA and the Master Builders Association of Western Pennsylvania (AIA-MBA Joint Committee) goes further. It recommends that the term as built "should not be used on drawings, contracts, correspondence or in discussion", and that record drawings be used instead (AIA-MBA Joint Committee, Section B-1).
Why do state DOTs and owners use the terms differently?
Because each owner wrote its own manual, and some changed their minds. Three public examples show the range:
| Owner | What "as-built" means there | What "record drawings" means there |
|---|---|---|
| Federal guide specification (UFGS 01 78 00) | The marked-up drawings the contractor keeps on site | The final compilation of the as-built drawings |
| Arizona Department of Transportation | A retired term, replaced in 2015 | The final set, prepared from the field red-lines under the resident engineer |
| City of Los Angeles, Bureau of Engineering | Plans drafted by the city's construction manager with the contractor's markups incorporated | The plans the contractor marks up during construction |
The federal definitions read: "As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the Contract Documents" and "The record drawings are the final compilation of actual conditions reflected in the as-built drawings" (UFGS 01 78 00).
Los Angeles reverses them: "Record Drawings are full size drawings (plans) which are marked up by the Contractor during construction to delineate the actual in-place construction conditions", while as-built plans are "prepared by the Bureau of Engineering's Construction Manager" (Los Angeles Bureau of Engineering).
Arizona's guidelines describe final record drawings as "formerly known as" as-built drawings, a change "adopted by ADOT on April 7th, 2015" (ADOT Record Drawing Guidelines). Read the definitions in your contract before you agree to deliver either set.
What are redlined drawings?
Redlined drawings, also called redline drawings or a red line markup, are prints marked by hand or in a PDF editor to show changes, traditionally in red. On a construction project, the redlines are the as-built markups. Arizona DOT defines them: "Field Red-Lines - The field red-lines are the changes or modifications that occurred during construction of the project." They "can include quantity adjustments, minor field modifications, sketches, added plan sheets, exhibits or anything that was done on a project that is outside of the original design and did not require a change order" (ADOT).
Colors carry meaning, and the conventions differ from owner to owner:
- Arizona DOT: "Change orders are shown in the record drawings in red", while "Addenda are typically shown in black on the record drawings since they occurred prior to the contract being awarded" (ADOT).
- Federal guide specification: "Use base colors of red, green, and blue", with red for deletions, green for additions and blue for items "requiring special information, coordination, or special detailing" (UFGS 01 78 00).
- Alabama State Military Department: "Mark record sets with erasable, red-colored pencil", and "Use other colors to distinguish between changes for different categories of the Work at the same location" (section 01 78 39).
Whatever the colors, write words next to the marks. The federal specification says: "Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision" (UFGS 01 78 00). Redlines of contracts and other legal documents, meaning tracked changes between drafts, are a different thing with the same name; this page covers drawings.
Who signs record drawings, and are they stamped?
Usually nobody seals them as a new design, because the designer did not verify the field conditions. Cornell's record drawings are not signed; they are "stamped or otherwise marked by the design team" as record drawings and dated (Cornell). Virginia's state building office is explicit: "The drawings are not required to be sealed and signed", but a statement of preparation "shall be affixed to each and every drawing sheet" (Virginia Department of General Services).
Other people certify other parts. Arizona puts the responsibility on its resident engineer, a licensed professional engineer who is "responsible for the field red-lines being recorded completely and accurately" and who confirms on a submittal form that the final record drawings "include all of the field changes" (ADOT). The Joint Committee adds one firm rule for sealed design documents: "Under no circumstance should such revisions to contract documents be made by anyone other than the Architect or Engineer whose seal they bear" (AIA-MBA Joint Committee).
| Who | What they sign or certify | Public example |
|---|---|---|
| Contractor | That the marked set is complete and current | Los Angeles: a signed certification with each monthly payment request |
| Owner's resident engineer | That the final record drawings include all field changes | Arizona DOT project submittal form |
| Architect or engineer of record | A statement or stamp saying how the record set was prepared, not a new design seal | Virginia statement of preparation; Cornell record stamp |
| Licensed surveyor | Measured locations and elevations of what was built, under seal | As-built surveys of utilities and site work |
For the measured side, see as-built survey.
Who is liable if record drawings are wrong?
Mostly whoever supplied the wrong information, which is why the documents say so. The AIA instructions state: "Because the As-constructed Record Drawings will be based on the Contractor's mark-ups, the Architect is not responsible for the accuracy or completeness of the As-constructed Record Drawings" (AIA B101-2017 instructions). Virginia's statement of preparation says "The A/E is not responsible for either errors in information provided by Contractor or others, or for information omitted by Contractor from its As-Built Drawings" (Virginia Department of General Services).
The Joint Committee explains the caution: the architect "should be careful never to imply that his drawings show the construction exactly as it has been built", because "much of the work indicated on any construction drawing is diagrammatic only" (AIA-MBA Joint Committee). A pipe drawn along a wall may run a foot away from it.
So treat record drawings as a strong guide, not a measurement. Before digging, drilling or cutting, locate what is there. Owners reduce the risk by having buried work located by survey before backfill, as Los Angeles does (Los Angeles Bureau of Engineering), and by checking the markups at every pay application. This page is general information, not legal advice: liability depends on your contracts and your state's law, so take a specific dispute to your counsel.
Example: one change from redline to record drawing (illustrative)
One fictional change on a small office project, traced through each document. Numbers and names are invented for this page.
| Step | Document | What it shows |
|---|---|---|
| 1. Question | RFI 027 from the mechanical contractor | The supply duct on sheet M-201 hits a beam at grid C-4; the contractor asks for a new route |
| 2. Answer | Architect's RFI response with sketch SK-M-05 | Drop the duct 6 inches and flatten it from 24 x 12 to 30 x 10 inches |
| 3. Contract change | Change order 04 | No change to the contract sum or time |
| 4. Field markup | As-built set, sheet M-201 | Old route struck through in red, new route drawn in green, note "per RFI 027 and SK-M-05" |
| 5. Monthly check | Pay application review | The owner's representative confirms the markup is on the set |
| 6. Record drawing | Record set, sheet M-201, marked as a record drawing and dated | New route drafted in, colors gone, revision note citing RFI 027 |
The record sheet shows the result. Only the RFI, the sketch and the redline show why the change was made, so keep the change order and RFI logs with the drawings.
Common mistakes with redlines and record drawings
Most disputes over record drawings start with a word nobody defined.
- Assuming everyone means the same thing by "as-built" and "record drawing". Put the definitions in the contract.
- Leaving record drawings out of the design contract, then asking the architect for them at closeout.
- Issuing record drawings for the changed sheets only, when the owner expects a complete set.
- Sealing record drawings as if the designer had verified the field conditions.
- Redlines with no reference to the RFI, change order or sketch behind them.
- Throwing away the redline set once the record set is drafted. It is the only proof of what the field recorded.
- Relying on record drawings for buried utilities without locating them first.
Are record drawings and redlines also a data asset?
Together with the records around them, they can be. AI data buyers have asked Origin for CAD files and drawing sets from architecture, engineering and construction firms, with years of revision history, and for the project records around them (RFIs, submittals, change orders). The value is in the revision trail: design intent, each change and what was built. A redline set kept next to its RFIs, change orders and the record drawing that resulted is that trail in one place.
What must come out first: client-confidential and security-sensitive drawings, personal data in title blocks and correspondence, and anything the firm does not own under its contracts. Ownership of drawings follows the design contract; see who owns architectural drawings and de-identifying company data.
Origin is an independent data partner. Your firm decides what is shared and signs any license itself, and a buyer may pay Origin when a deal closes.
Does your company hold records like these? See what your data is worth.
Common questions
Are record drawings the same as as-builts?
The words are often used for the same set, but strictly they differ. As-builts are the contractor's field markups showing what changed. Record drawings are the clean, complete set compiled from those markups and the change documents, usually by the designer. Some owners, such as the City of Los Angeles, use the two terms the other way round.
What does redlined drawings mean in construction?
Redlined drawings are contract prints marked up, traditionally in red, to show changes made during construction: moved items, added work, deleted work and field fixes. They are the raw as-built record. Arizona DOT calls them field red-lines and includes quantity adjustments, minor field modifications, sketches and added sheets that did not need a change order.
Do record drawings need to be stamped by an engineer?
Usually not as a new design. Because the designer compiles record drawings from the contractor's markups without checking them in the field, many owners do not require a seal. Virginia's state building office says they need not be sealed and signed but must carry a statement of preparation, and Cornell marks them as record drawings and dates them.
Who prepares record drawings, the contractor or the architect?
It depends on the contract. The contractor always provides the markups. Under the AIA owner-architect agreement, the architect prepares as-constructed record drawings only as a supplemental service the owner selects. Some owners give the job to the contractor, and some public agencies, such as the Los Angeles Bureau of Engineering, draft the final set themselves.
What colors are used for redline markups on drawings?
Red is traditional, but conventions vary. The federal guide specification uses red for deletions, green for additions and blue for special notes, and asks for a legend if other colors are used. Arizona DOT shows change orders in red and addenda in black on record drawings. Whatever the scheme, write a short note next to each change.
Can you rely on record drawings to find underground utilities?
Only as a guide. Record drawings rest on the contractor's markups, and many runs were drawn diagrammatically, so actual positions can differ. Have the lines located before anyone digs. Owners can make the record more reliable by requiring buried work to be located by survey before backfill, as the City of Los Angeles does.
What is the difference between conformed drawings and record drawings?
Conformed drawings are the construction documents updated with the addenda and accepted alternates from bidding, issued before construction starts; the AIA notes they are commonly called issued for construction documents. Record drawings come at the end and show what was built, based on the contractor's markups, change orders and RFI answers. One is the starting point; the other is the finish.
Is the architect liable for errors in as-built drawings?
Under the standard AIA wording, the architect is not responsible for the accuracy or completeness of as-constructed record drawings, because they are based on the contractor's markups. Owner forms such as Virginia's statement of preparation say the same. Liability for a specific error depends on your contracts and state law, so take a real dispute to counsel.
Sources and further reading
- Cornell Facilities and Campus Services: As Built vs. Record Drawings
- AIA Contract Documents: Instructions, B101-2017 Standard Form of Agreement Between Owner and Architect
- AIA Contract Documents: How AIA Contract Documents Address As-Built Drawings
- AIA Document A201-2017, General Conditions of the Contract for Construction (sample)
- AIA-MBA Joint Committee: Drawings and Specifications, Section B-1
- WBDG: UFGS 01 78 00, Closeout Submittals
- Arizona Department of Transportation: Record Drawing Guidelines
- City of Los Angeles, Bureau of Engineering: 25.2 Record Drawings and As-Built Plans
- Virginia Department of General Services: DEB Notice 071708, Record Drawings
- Alabama State Military Department: Section 01 78 39, Project Record Documents
- South Carolina Office of State Engineer: AIA B101-2017, SCOSE version (comparative)