An engineering change order (ECO) is the approved instruction to change a released design: which parts and documents change, why, what the change is, when it takes effect and what happens to existing stock. It usually follows an engineering change request (ECR) and is announced by an engineering change notice (ECN), though many companies use the names differently. The template below has the fields a change board needs, with a filled-in example of a dimension change that ripples through a drawing, a BOM and inspection.
- ECR asks, ECO decides and instructs, ECN tells everyone. Write down which names your company uses.
- Every ECO lists all affected documents, not just the drawing: BOM, routings, inspection plans, manuals.
- Effectivity (from which serial, lot or date) and disposition of existing stock are part of the decision.
- Revision letters on the drawing should trace back to the ECO number that caused them.
ECR vs ECO vs ECN
Terms vary: some companies call the whole process an ECN. The Wikipedia summary describes an ECO as something that "is an artifact used to implement changes to components or end products" (Wikipedia). It also quotes a configuration-management definition: a "document approved by the design activity that describes and authorizes the implementation of an engineering change to the product and its approved configuration documentation". In federal contracting, the design activity is "an organization, Government or contractor, that has responsibility for the design and configuration of an item" (FAR 46.101). The most common split is below.
| Document | Purpose | Who raises it | Output |
|---|---|---|---|
| ECR (engineering change request) | Proposes a change and the reason | Anyone: engineering, production, quality, a customer | Accepted or rejected for study |
| ECO (engineering change order) | Defines and authorizes the change | Engineering, approved by the change board | New revisions of drawings, models, BOMs and documents |
| ECN (engineering change notice) | Announces the released change | Document control | Notice to production, purchasing, quality and service |
ECO template: the fields to include
Download the engineering change order template (CSV); it opens in Excel or Google Sheets and includes one filled-in row. The fields:
| Field | What to record |
|---|---|
| ECO number | Unique ID, and the ECR it answers |
| Title and originator | Short name of the change and who wrote it |
| Reason | Design error, customer request, cost, supplier or material change, safety, corrective action (with NCR or CAPA number) |
| Classification | Your change classes, for example minor or major, and whether the customer must approve |
| Affected items | Part numbers with current and new revision |
| Description of change | Before and after, with marked-up drawing or model views |
| Affected documents | Drawings, 3D models, BOMs, routings, work instructions, inspection plans, manuals, software |
| Effectivity | From which date, lot, serial number or work order the change applies |
| Existing stock disposition | Use up, rework, scrap or return, for raw material, work in progress, finished goods and field units |
| Cost and schedule impact | Tooling, scrap, requalification, lead time |
| Verification | Tests, first article or analysis needed before release |
| Approvals | Names, roles and dates: engineering, quality, manufacturing, purchasing, customer if required |
| Implementation record | Date each affected document was released and each department confirmed |
| Status | Draft, in review, approved, released, implemented, closed |
Filled-in ECO example: a dimension change that ripples (illustrative)
An illustrative example, not a real company record. NCRs show the hole on a bracket is hard to hold in tolerance and the mating panel has slack, so engineering widens the tolerance.
| Field | Entry |
|---|---|
| ECO number | ECO-1187, answering ECR-0932 |
| Reason | Corrective action: NCR-2026-0142 and two earlier NCRs on the same hole; CAPA-0219 |
| Classification | Minor for form, fit and function; customer notification only under the supply agreement |
| Affected items | BRK-2207 rev C to rev D; assembly ASM-310 rev F to rev G (drawing note only) |
| Description | Hole position tolerance changed from plus or minus 0.10 mm to plus or minus 0.20 mm; tolerance stack-up attached |
| Affected documents | BRK-2207 drawing and model, ASM-310 drawing note, inspection plan IP-2207, supplier PO terms |
| Effectivity | All BRK-2207 purchase orders placed after release |
| Existing stock | Rev C stock usable as is (tighter than rev D); no rework |
| Verification | Fit check of 10 parts at the new limits on the assembly fixture |
| Approvals | Design engineer, quality engineer, manufacturing engineer, purchasing; dates recorded |
| Status | Released 18 March, ECN-1187 sent to purchasing, receiving inspection and the supplier |
See the matching NCR in the NCR template examples.
The engineering change process: routing and the change board
Route each ECO by its class. A minor change that touches one drawing can go to engineering and quality. A change to form, fit or function, to a safety-related part, or to anything a customer has approved goes to a change control board (CCB): engineering, quality, manufacturing, purchasing and service, with the customer where the contract requires.
Aviation has a defined split. A type-design change is "minor" if it "has no appreciable effect on the weight, balance, structural strength, reliability, operational characteristics, or other characteristics affecting the airworthiness of the product", and every other change is a major change (14 CFR 21.93). FAA production approval holders also need procedures "for controlling design data and subsequent changes to ensure that only current, correct, and approved data is used" (14 CFR 21.137).
Revision control: keeping drawings traceable
Each released ECO should produce new revisions of every affected document, and each revision block should name the ECO. In the US the common reference is ASME Y14.35, now titled "Revision of Engineering Product Definition Datasets and Associated Documents". ASME describes it this way: "This Standard defines the practices for revising drawings and associated documents and establishes methods for identification and recording revisions." Buy the standard for the rules on revision letters and records.
The same discipline applies to documents beyond drawings. FAA production approval holders must control "quality system documents and data and subsequent changes to ensure that only current, correct, and approved documents and data are used" (14 CFR 21.137). In a PDM or PLM system (SolidWorks PDM, Vault, Windchill, Teamcenter), run the ECO as a workflow so the release of new revisions and the ECO approval happen together.
Linking ECOs to NCRs and test results
Many ECOs exist because of quality problems: a tolerance nobody can hold, a material that cracks, a part that fails a test. Record the NCR, CAPA or 8D number on the ECO, and the ECO number back on the corrective action. Attach the verification test results to the ECO itself.
That two-way link is what lets an engineer, years later, see why a dimension is what it is, and stops the next person from tightening it back.
Common ECO mistakes
Most ECO problems are missing information, not wrong engineering.
- Affected documents incomplete: the drawing changes but the inspection plan, BOM or work instruction does not.
- No effectivity, so production builds a mix of old and new.
- Existing stock and open purchase orders forgotten.
- Reason field left as "update" with no link to the NCR, customer request or cost study.
- Revision letters raised without naming the ECO, so the history cannot be reconstructed.
- Changes made in the CAD model without an ECO, then discovered at the next release.
- Customer approval skipped on a change the contract classes as major.
Where the change history sits in common PDM and PLM systems
When an ECO process runs inside a PDM or PLM system, the change records and their reasons can be kept next to the revised files, so exporting them is part of exporting the design. The system guides cover each one in detail:
| System | Where change records live | Guide |
|---|---|---|
| SOLIDWORKS PDM | Workflow states, check-in and state-change comments; file lists by CSV through the Report Generator in PDM Professional | SolidWorks PDM vault guide |
| PTC Windchill | Problem reports, change requests and change notices linked to the parts they revise | Creo and Windchill data guide |
| Siemens Teamcenter | Change objects and workflow records beside item revisions and BOM baselines | NX and Teamcenter data guide |
If ECOs were kept in spreadsheets or email instead, export them with their numbers so each change can still be matched to the drawing revision it produced.
Your change history is also a data asset
A long ECO history, with each revision of the model and drawing tied to the reason, the NCRs behind it and the test that verified it, shows how a design actually evolved. That is the part of engineering knowledge that never appears in a finished drawing.
AI developers building tools for quality and engineering work ask for this kind of linked, outcome-bearing history; where a license is agreed, it is de-identified and under written terms. Customer-owned drawings, export-controlled technical data and personal details stay out (see the export-control checklist and how to de-identify records). The guide for engineered-product manufacturers covers what is in scope and who signs; licensing CAD and engineering data covers the design side.
If your company keeps years of quality and engineering change records, the guide for engineered-product manufacturers explains what AI developers ask for and who signs. To see what yours could be worth, describe them in six questions; no files or system access needed.
Common questions
What is an engineering change order?
An engineering change order (ECO) is the approved instruction to change a released design. It lists the affected parts and documents, the reason, the change itself, when it takes effect, what happens to existing stock, and who approved it.
What is the difference between an ECN and an ECO?
In many companies the ECO defines and authorizes the change and the ECN announces the released change to everyone affected. Some companies use ECN for the whole process. Write down which terms your company uses and use them consistently.
Who approves an engineering change order in a manufacturing company?
Minor changes are usually approved by engineering and quality. Changes to form, fit, function, safety or customer-approved designs go to a change control board with engineering, quality, manufacturing and purchasing, plus the customer when the contract requires it.
What triggers a new drawing revision?
Any released change to the drawing content, under an approved ECO. Each new revision should name the ECO in its revision block. ASME Y14.35 sets the common US practice for revising drawings and recording revisions.
How should engineering change orders be numbered?
Use a unique sequential number that never repeats, for example ECO-1187, and record the ECR it answers. Avoid encoding part numbers or dates into the ID; put those in fields so they can be searched.
Can a PDM or PLM system run the ECO process?
Yes. SolidWorks PDM, Autodesk Vault, Windchill, Teamcenter and similar systems can run ECO workflows, so approval and the release of new revisions happen together. Keep the reason, the linked NCRs and the test evidence inside the workflow record.
Are a manufacturer's engineering change histories valuable outside the company?
They can be. A long, linked history of design changes with reasons and test results shows how designs evolve, which is hard to find anywhere public. Customer-owned designs and export-controlled data must stay out of anything shared.
What is an engineering change request (ECR)?
An ECR is the proposal to change a released design: what should change and why. Anyone can raise one. If the change board accepts it, engineering writes the engineering change order that defines and authorizes the change.
Can the ECO template be used in Word or as a printed form?
Yes. The CSV opens in Excel or Google Sheets, and the fields work as a Word table or a printed ECO form. Keep the ECO number, affected documents, effectivity, stock disposition and approvals on every format, and link each ECO to the ECR it answers.
What is an engineering change notice (ECN)?
In many companies the ECN is the notice that tells production, purchasing, quality and service that an approved change has been released, with its effectivity. Some companies use ECN as the name for the whole change process, so write down which meaning yours uses.
Sources and further reading
Origin Data Partners is an independent data partner. We work with buyers, and a buyer may pay us when a deal closes.
- Wikipedia: Engineering change order (summary article)
- eCFR: 48 CFR 46.101 (FAR), quality assurance definitions
- ASME: Y14.35, Revision of Engineering Product Definition Datasets and Associated Documents
- eCFR: 14 CFR 21.93, classification of changes in type design
- eCFR: 14 CFR 21.137, quality system (production approval holders)