Bill of Materials Template: EBOM vs MBOM and Indented BOMs

Bill of materials template and example: the columns, an indented BOM, a CSV layout for Excel, EBOM vs MBOM, phantom items, and what BOMs are worth to AI.

Short answerChecked

A bill of materials template lists every item needed to build one parent assembly: find number, part number, description, quantity, unit of measure and revision, plus reference designators for electronics and make or buy. An indented BOM shows the full multilevel structure. The engineering BOM (EBOM) is the as-designed structure and the manufacturing BOM (MBOM) the as-planned structure the plant builds from.

Digital calipers on a quality inspection report on a factory workbench
Key points
  • Core columns: find number, level, part number, description, quantity, unit of measure, revision and make or buy.
  • An indented BOM shows every level; a parts-only BOM flattens everything into one list.
  • The EBOM follows the design; the MBOM follows how the product is built, and the two are kept in step.
  • Tie every BOM change to an engineering change order and check where-used before you change a part.

Bill of materials template: the columns and what goes in each

A BOM is a list of the items "associated with a parent item and information about how each item is related to its parent" (Oracle). SAP describes it as a directory holding "the name, reference number, quantity, and unit of measure" of each constituent part (SAP Learning). The template below uses those core fields plus the ones defense and space programs require, with the source of each definition.

ColumnWhat goes in itDefined by
LevelDepth in the structure: 0 for the top assembly, 1 for its direct children, and so onDoD BOM data item (indenture level)
Find numberThe item's tag on the assembly drawing, so a line can be found on the pictureDoD BOM data item
Part numberThe unique identifier of the item, the same in CAD, ERP and purchasingSAP (reference number)
DescriptionNoun first, then modifiers: "Screw, M3 x 8, socket head, stainless"SAP (name)
QuantityHow many per one parent, not per orderSAP
Unit of measureEach, mm, kg, liter; required for anything not counted in piecesSAP
RevisionThe revision of the part this line calls forDoD BOM data item
Reference designatorsFor electronics: R1, R2, C5; several parts may share one find numberNASA MSFC-STD-555J
Make or buy (supply type)Made in house or purchased; purchased items stop the explosionOracle
Material, supplier, notesMaterial specification, approved supplier, special handlingCommon practice

Sources: DoD DI-PSSS-81656A, NASA MSFC-STD-555J, PDF, Oracle and SAP Learning. The DoD data item also sets the file type for a delivered BOM: "an electronically editable, machine-readable Comma Separated Values (CSV) text file".

Bill of materials example: an indented BOM for a small assembly

An invented example of a sensor enclosure with a circuit board inside. Part numbers and quantities are illustrative. Level 2 lines belong to the level 1 line above them.

LevelFind no.Part numberDescriptionQtyUoMRevMake or buyRef. des.
0100-0001Enclosure assembly, sensor1EACMake
11100-0010Housing, machined, aluminum 60611EABMake
12100-0020Circuit board assembly, sensor1EADMake
22.1200-0100Printed circuit board, bare, 4 layer1EACBuy
22.2210-0005Resistor, 10 kOhm, 1%, 06034EAABuyR1-R4
22.3220-0012Capacitor, 0.1 uF, 50 V, 06032EAABuyC1, C2
13100-0030Gasket, silicone, die cut1EAABuy
14300-0004Screw, M3 x 8, socket head, stainless4EAABuy
15400-0002Thread locker, medium strength0.2MLABuy
The same BOM as a CSV file you can open in Excel or import into an ERP. Fields sit in double quotes, in line with the DoD data item's rule for text fields.
"Level","Find No","Part Number","Description","Qty","UoM","Rev","Make/Buy","Ref Des"
"0","","100-0001","Enclosure assembly, sensor","1","EA","C","Make",""
"1","1","100-0010","Housing, machined, aluminum 6061","1","EA","B","Make",""
"1","2","100-0020","Circuit board assembly, sensor","1","EA","D","Make",""
"2","2.1","200-0100","Printed circuit board, bare, 4 layer","1","EA","C","Buy",""
"2","2.2","210-0005","Resistor, 10 kOhm, 1%, 0603","4","EA","A","Buy","R1-R4"
"2","2.3","220-0012","Capacitor, 0.1 uF, 50 V, 0603","2","EA","A","Buy","C1, C2"
"1","3","100-0030","Gasket, silicone, die cut","1","EA","A","Buy",""
"1","4","300-0004","Screw, M3 x 8, socket head, stainless","4","EA","A","Buy",""
"1","5","400-0002","Thread locker, medium strength","0.2","ML","A","Buy",""

The thread locker shows why the unit of measure column matters: a quantity of 0.2 means nothing without ML. The bare board is bought, so the BOM stops there even though the board vendor has its own bill.

Single-level vs indented BOM: which one do you need?

A single-level BOM lists only the direct children of one parent. "An indented (multilevel, exploded) manufacturing or engineering bill of material displays the structure of a manufacturing or engineering item" down every level (Oracle). CAD tools offer the same choices. SOLIDWORKS BOM tables come as "Top-level only, Parts only, or Indented" (SOLIDWORKS blog), and Autodesk Inventor's parts-only view "shows all components in a flat list" in which normal assemblies are not displayed (Inventor help).

Use the indented view to plan builds and kits, the parts-only view to buy, and the top-level view on an assembly drawing. The reverse lookup is where-used: "an imploded list of all the using assemblies for a specified component" (Oracle). Run it before you change or obsolete any part.

EBOM vs MBOM: what is the difference?

PTC's Windchill help gives the shortest definitions: the eBOM is "the as-designed product structure" and the mBOM "the as-planned product structure", a list of "all the parts and their quantities required to build the product" (PTC Windchill help). Siemens puts it as function against assembly: "the EBOM emphasizes how materials and parts relate to the product's functional design", while "the MBOM reflects how the materials and parts build a complete product" (Siemens). ERP systems keep them apart too; SAP lets you "maintain separate BOMs for different areas within your company, such as design or production" (SAP Library).

EBOM (engineering)MBOM (manufacturing)Service BOM
RepresentsThe product as designedThe product as it will be builtThe product as it is serviced
Usually lives inCAD and PDM or PLMERP or MES, often derived in PLMPLM or service systems
Typical structureBy function and CAD assemblyBy build sequence, station or kitBy replaceable unit
AddsDesign parts and their revisionsConsumables, packaging, labels, process materialsSpares and kits
Changes whenAn engineering change is releasedThe process or plant changes as wellService plans change

A service BOM, in PTC's words, is "a view of one or more source BOMs (typically engineering and manufacturing BOMs) used to represent the service perspective" (PTC Windchill help). In the example above, the EBOM would stop at the designed parts, and the MBOM would add the thread locker and regroup lines by assembly station.

What are phantom, purchased and reference items in a BOM?

CAD tools tag each component with a BOM structure, and the tag decides what shows up as a line. In Autodesk Inventor, phantom components "exist in the design, but are not line items in a bill of materials"; purchased components "are considered a single BOM line item, even though it is a part or an assembly"; and reference components, used for construction geometry or context, "are ignored in the BOM" (Inventor help).

ERP planning follows the same logic for purchased items: "The planning process does not pass demand down from purchased items to lower level components" (Oracle). A motor bought complete is one line, even if your CAD model shows its internals. Getting these tags right in CAD saves a manual clean-up every time the BOM is exported.

How should BOM revisions tie to engineering change orders?

Every BOM change should come through a change order. Oracle's engineering module states the purpose plainly: "Engineering Change Orders (ECOs) enable you to control new item revisions and bill of material changes" (Oracle). The ECO records what changed, why and when it takes effect; the BOM's revision column shows the result. Our engineering change order template lays out the fields.

A simple discipline keeps the two in step: no BOM edit without an ECO number, a where-used check before any part changes, and an effectivity date or serial number on each change, so anyone can rebuild the BOM as it stood for a given unit.

Which bill of materials mistakes cause wrong builds?

These cause most of the shortages, wrong builds and audit findings that trace back to a BOM:

  • Quantities per order instead of per parent assembly.
  • No unit of measure on liquids, wire, tubing or sheet stock.
  • Different part numbers for the same item in CAD and ERP.
  • Descriptions that start with a brand name instead of the noun, which makes duplicates hard to spot.
  • BOM edits made directly in ERP with no change order behind them.
  • Phantom or reference components left untagged, so CAD exports carry lines nobody buys.
  • Old revisions overwritten instead of kept, which loses the record of what was built when.

Can your company get paid by AI companies for its BOMs and product structures?

Your company can get paid for these records. AI developers working on design and manufacturing models need real product structures, and these are hard to find. One research team released the Fusion 360 Gallery assembly dataset, with "the underlying assembly graph structure", to support research (arXiv 2111.12772). A 2026 paper notes that "industrial CAD data are typically proprietary and require substantial expertise and modeling effort" (arXiv 2606.01702). Another, on mapping BOMs with language models, worked from documents that carry "the supplier of the component and the material name" (arXiv 2502.07418).

AI data buyers publish payouts of $100K to $5M for established companies' records, and most ask for 30 or more staff. A BOM on its own is a list. Years of BOMs linked to their CAD revisions, change orders and build records show how real products are designed, changed and made, and that history is what a buyer pays for. Our guide to licensing CAD and engineering data covers ownership and customer designs, and the CAD archive value calculator places an archive against published buyer requirements.

We help you license your data. Origin Data Partners is an independent data partner that helps business owners value and license their company records: the company pays Origin nothing, and a buyer may pay Origin when a deal completes. Describe the records first: products, years of BOM history, the PLM or ERP that holds them, and whether revisions and ECOs are linked. Then see what your company's records could be worth. Not the owner? Advisers can introduce the company.

How we checked this

We read every source on this page on 21 November 2026: Oracle's Bills of Material and Engineering user guides, SAP's training and library pages, PTC Windchill and Autodesk Inventor help, Siemens' MBOM page, a SOLIDWORKS blog post on BOM types, the US Department of Defense BOM data item and NASA's MSFC-STD-555J, and arXiv papers on assembly datasets and BOM mapping.

What we could not verify: the current SOLIDWORKS and SAP help portals, which load their text with scripts our checker cannot read, so older SAP library pages and the SOLIDWORKS blog stand in for them. The material and supplier columns are common practice rather than a requirement in any one standard. The example BOM is invented.

Common questions

What should a bill of materials include?

At minimum: a find number, part number, description, quantity per parent and unit of measure for each line, plus the revision of the part it calls for. Multilevel BOMs add a level or indenture number. Electronics BOMs add reference designators, and most manufacturers add make or buy, material and approved supplier. Keep part numbers identical across CAD, ERP and purchasing.

What is an indented bill of materials?

An indented BOM shows the whole product structure, every subassembly and the parts inside it, with each level indented or numbered under its parent. It is also called a multilevel or exploded BOM. A single-level BOM shows only one parent's direct children, and a parts-only BOM flattens everything into one list without subassemblies.

What is a phantom assembly in a BOM?

A phantom is a grouping that exists in the design or structure but is not built or stocked as its own item. Its children are pulled straight into the parent assembly, and the phantom itself is not a line that anyone makes or buys. It keeps CAD models organized without adding work orders or inventory transactions in ERP.

What is a where-used report?

It is the reverse of a BOM explosion: for one component, it lists every assembly that uses it, at every level. Engineers run it before changing or obsoleting a part, to see which products, drawings and open orders the change will touch. Most ERP and PLM systems produce it directly from the BOM data.

How do you make a bill of materials in Excel?

Set up one row per BOM line with columns for level, find number, part number, description, quantity, unit of measure, revision, make or buy and reference designators. Save it as CSV with every field in quotes so commas in descriptions survive import. Use one sheet per top assembly and a level column rather than merged cells, so the file can be sorted and imported.

What is a service BOM?

A service BOM describes a product the way field service sees it: replaceable units, spare parts and service kits rather than the design or build structure. It is usually derived from the engineering and manufacturing BOMs and kept in step with them, so a technician orders the right spare for the revision installed at a customer site.

Can a manufacturer license its BOM history to AI companies?

Yes, where the company owns the designs. BOMs linked to CAD revisions, change orders and build records show how real products evolve, which AI developers cannot get from public data. Customer-owned designs, supplier pricing and export-controlled items should be kept out. Start by describing the products, years of history and systems involved, without sharing files.