# First Article Inspection Report: AS9102 Forms and Example

> What a first article inspection is, how AS9102 Forms 1, 2 and 3 are filled in, a worked example, full vs partial FAI, and who owns the reports.

Canonical: https://origindatapartners.com/guides/first-article-inspection-report
By: Origin Data Partners
Status: Published
Published: 2026-11-15
Updated: 2026-11-15
Sources checked: 2026-11-15

## Quick answer

A first article inspection (FAI) checks one part from the first production run against every requirement on the drawing, to show the process can make the part correctly. In aerospace the result is written up as a first article inspection report (FAIR) on the three AS9102 forms: Form 1 for the part, Form 2 for materials, special processes and functional tests, and Form 3 for every characteristic.

## Key points

- An FAI proves the process, not just the part: it uses production tooling, methods and people.
- Form 3 needs one line for every design characteristic, including drawing notes.
- A change to design, process, tooling, source or location needs a partial FAI on what changed.
- A two-year gap in production normally calls for a new FAI.

## What is a first article inspection, and when is one required?

A first article inspection is a complete, documented check of a part from the first production run. One supplier procedure states the aim plainly: "The primary purpose of FAI is to validate the production processes are capable of producing parts and assemblies that meet engineering and quality requirements" ([Jedco supplier procedure](https://jedinc.com/wp-content/uploads/2023/11/TM-50110J-First-Article-Inspection.pdf)). Every dimension, note, material and process on the drawing is accounted for, and the evidence is collected in a first article inspection report, or FAIR.

In aerospace and defence the format is AS9102, published by SAE and known as 9102 in the International Aerospace Quality Group series. Customers call it up on the purchase order, and suppliers pass it down to their own sub-tier suppliers.

An FAI is needed for a new part, and again when something changes. The same procedure lists the triggers: a design change that affects fit, form or function; "a change in manufacturing source(s), process(es), inspection method(s), location of manufacture or tooling"; an event that may affect the process; a corrective action needed to complete an earlier FAI; and a gap in production. On the last one it says "a lapse in production for two years shall require an update for any characteristics that may be impacted by the inactivity" ([Jedco](https://jedinc.com/wp-content/uploads/2023/11/TM-50110J-First-Article-Inspection.pdf)).


## What are AS9102 Form 1, Form 2 and Form 3?

The report is three linked forms. The supplier procedure names them: "Form 1: Part Number Accountability", "Form 2: Product Accountability - Materials, Special Processes, and Functional Testing" and "Form 3: Characteristic Accountability, Verification and Compatibility Evaluation" ([Jedco](https://jedinc.com/wp-content/uploads/2023/11/TM-50110J-First-Article-Inspection.pdf)). The descriptions below are ours. Field numbers and wording differ between revisions of the standard, so work from the revision your purchase order names.

| Form | What it accounts for | Main entries |
| --- | --- | --- |
| Form 1 | The part and the report itself | Part number, name, serial number, part and drawing revision levels, manufacturing process reference, supplier, purchase order, whether the FAI is full or partial with the reason, the lower-level parts in an assembly with their own FAI references, whether the FAI is complete, signatures and dates |
| Form 2 | What went into the part | Each material with its specification and certificate, each special process (heat treat, plating, welding, non-destructive testing) with the approved source and certificate, and each functional test procedure with its report |
| Form 3 | Every design characteristic | Characteristic number matching the balloon on the drawing, drawing sheet and zone, the requirement with its tolerance, the measured result, the gauge or tooling used, and any non-conformance reference |

You do not have to use the standard's own layout. The International Aerospace Quality Group's FAQ says "forms other than those contained in the Appendix may be used; however they must contain all 'Required' and 'Conditionally Required' information and have the same field reference numbers", and that reports and drawings may be attached and referenced on the forms ([IAQG FAQ](https://endevco.com/contentstore/mktgcontent/endevco/uploads/2019/02/AS9102-frequently-asked-questions1.pdf)).


## First article inspection report example: ballooned drawing to Form 3

A fictional example shows the work. A machine shop makes an aluminium bracket, part 7714-203 revision B, from 6061-T6 plate, then sends it out for anodising. The drawing has 28 characteristics once every dimension and note is ballooned. The steps were:

- Balloon the drawing: number every dimension, tolerance, note and specification callout, 1 to 28.
- Form 1: enter the part, revisions, purchase order and process router number; mark it a full FAI.
- Form 2: list the plate with its mill certificate and the anodise with the processor's certificate and approval.
- Form 3: one line per balloon, with the actual measured value, not "OK" or "pass", for anything with a number.
- Attach the ballooned drawing, the CMM report and the certificates, and reference them on the forms.

| Char. no. | Sheet / zone | Requirement | Result | Gauge | NC ref. |
| --- | --- | --- | --- | --- | --- |
| 1 | 1 / B3 | Length 120.00 ±0.10 mm | 120.04 | CMM |  |
| 7 | 1 / C4 | Hole Ø6.35 +0.03/-0.00 mm, 4 places | 6.36, 6.36, 6.37, 6.36 | Pin gauge set and CMM |  |
| 12 | 1 / D2 | True position Ø0.10 to datums A, B, C | 0.06, 0.04, 0.07, 0.05 | CMM, report 2231 |  |
| 19 | 1 / A5 | Surface finish 1.6 µm Ra max | 1.1 | Profilometer |  |
| 24 | 2 / note 3 | Anodise per the specification on the drawing, Type II, Class 1 | Conforms, certificate 88417 | Processor certificate |  |
| 27 | 2 / note 6 | Part mark per the specification on the drawing | Conforms | Visual |  |
| 28 | 2 / note 7 | Break sharp edges 0.2 to 0.5 mm | 0.6 at one edge | Optical comparator | NCR-0412 |

Fictional data. Characteristic 28 failed, so the report was marked "FAI not complete". The shop corrected the deburr step and ran a partial FAI on characteristic 28 from the next lot.


## Full FAI vs partial (delta) FAI: which one do you need?

A full FAI covers every characteristic. A partial FAI, often called a delta FAI, covers only the characteristics affected by a change and refers back to the earlier report. The IAQG's FAQ explains the baseline field on Form 1 as "the previous FAI part number, or approved configuration, including revision level, to which a partial FAI is performed" ([IAQG FAQ](https://endevco.com/contentstore/mktgcontent/endevco/uploads/2019/02/AS9102-frequently-asked-questions1.pdf)).

Say why it is partial. One aerospace customer's guidance is blunt: "Detailed explanation for the partial is required for all partial FAIs" ([GKN Aerospace](https://gknaerospace.com/media/mpibej0a/as9102-first-article-inspection-report-common-mistakes.pdf)). After a gap of two years or more, the FAQ's answer is that "normally, a Full FAI would be required", and a supplier that chooses a partial one has to justify it in its procedure and on the form ([IAQG FAQ](https://endevco.com/contentstore/mktgcontent/endevco/uploads/2019/02/AS9102-frequently-asked-questions1.pdf)).

| Situation | Usual answer |
| --- | --- |
| New part number | Full FAI |
| Drawing revision changes three dimensions | Partial FAI on those three and anything they affect |
| New fixture or a move to another machine | Partial FAI on the characteristics that fixture or machine produces |
| New plating supplier | Partial FAI on Form 2 and the plated characteristics |
| Work moved to another plant | Full FAI unless the customer agrees otherwise |
| No production for two years or more | Normally a full FAI |

The last column is a guide. Your customer's quality requirements decide.


## FAI vs PPAP vs first article testing: what is the difference?

They answer the same question for different customers. Aerospace primes ask for an AS9102 FAI. Automotive customers ask for PPAP, which AIAG calls "the industry standard for defining the production part approval process" ([AIAG](https://www.aiag.org/training-and-resources/manuals/details/PPAP-4)) and which adds process FMEAs, control plans, capability studies and a signed warrant; see [PPAP in manufacturing](https://origindatapartners.com/guides/ppap-in-manufacturing). A shop that serves both keeps both.

A third meaning comes from US government contracts. Under the Federal Acquisition Regulation, "first article testing and approval" is a contract requirement that "ensures that the contractor can furnish a product that conforms to all contract requirements for acceptance" ([FAR 9.302](https://www.acquisition.gov/far/9.302)). It can involve government-witnessed tests and a formal approval before production, and it is separate from the AS9102 report even when both apply to the same part.


## Where are FAI reports and CMM output stored, and for how long?

A FAIR is a bundle: the three forms, the ballooned drawing, the CMM report, material and process certificates, functional test reports and any non-conformance. Shops keep it as a PDF package in the quality system or ERP against the work order, in dedicated first-article software that balloons the drawing and fills Form 3, or on a customer portal. The CMM program and its raw output usually sit on the metrology computer, which is the piece most often lost.

Retention is set by the customer and the contract, not by a single rule that fits every shop. Aerospace purchase orders and supplier quality manuals commonly state a retention period for quality records and require the customer's permission before records are destroyed. Check the quality clauses on your purchase orders and keep the FAIR for at least as long as the longest of them.


## Common mistakes on an AS9102 report

Customers publish their own lists of what gets a report rejected, and they overlap heavily ([GKN Aerospace](https://gknaerospace.com/media/mpibej0a/as9102-first-article-inspection-report-common-mistakes.pdf)). Whatever the list, "please review your customer's requirements for anything not covered by AS9102".

- Quoting the wrong part or drawing revision on Form 1.
- Leaving out drawing notes and specification callouts. They are characteristics too.
- Writing "pass" or "conforms" where a measured value is required.
- Reporting one value for a feature that appears in several places.
- No gauge or tooling named against a result.
- A partial FAI with no reason and no baseline report referenced.
- Special process sources on Form 2 that are not on the customer's approved list.
- Sub-assembly and detail parts with no FAI of their own referenced on Form 1.
- Signing the report as complete while a non-conformance is still open.


## Your inspection records are also a data asset

An FAI package ties a drawing to the way a part was made and to what was measured, characteristic by characteristic. Years of them, with the work orders and non-conformances around them, show how real parts deviate and how a shop responds. According to one buyer's public listings, read 15 November 2026, "work orders with inspection reports" is one of three record sets that qualify a manufacturer, with CAM programs plus setup sheets and machine alarm logs plus process data, over several years of history. The same listings put the published range for a manufacturing company at $100,000 to $1.5 million. Read that as a ceiling that depends on record types and history, not a typical outcome. Origin Data Partners is an independent data partner that helps a shop find out whether its records fit a request like this.

Most of the work is deciding what is yours. The listings name "data restricted by customer contracts" as not a fit. The customer's drawing and specifications belong to the customer, and aerospace purchase orders usually restrict any disclosure of them. Defence work adds export control: the ITAR definition of technical data "includes information in the form of blueprints, drawings, photographs, plans, instructions, or documentation" ([22 CFR 120.33](https://www.ecfr.gov/current/title-22/section-120.33)), and a ballooned drawing or a Form 3 that reproduces its requirements can fall inside it. Start with the [ITAR and EAR checklist](https://origindatapartners.com/guides/itar-ear-checklist-cad-data-ai). Measurement results, process sheets and CMM programs for your own products, or for commercial work whose contracts allow it, are the realistic starting point. This page is general information, not legal advice.

Related guides: [machine shop CNC and CAM files](https://origindatapartners.com/guides/machine-shop-cnc-cam-files-ai), [licensing manufacturing quality records](https://origindatapartners.com/guides/license-manufacturing-quality-records-ai), the [PFMEA template](https://origindatapartners.com/guides/pfmea-template) and [contract manufacturer design data](https://origindatapartners.com/guides/contract-manufacturer-design-data-ai).

Does your company hold records like these? [See what your data is worth](https://origindatapartners.com/check-fit).


## Questions and answers

### What is a first article inspection report (FAIR)?

It is the documented result of a first article inspection: evidence that one part from the first production run was checked against every drawing requirement. Under AS9102 it consists of three forms plus attachments such as the ballooned drawing, certificates and the CMM report.

### What goes on AS9102 Form 3?

One line for every design characteristic: its number matching the ballooned drawing, where it is on the drawing, the requirement and tolerance, the actual result, the gauge or tooling used and any non-conformance number. Drawing notes count as characteristics.

### What is the difference between FAI and PPAP?

Both show that a production process can make a conforming part. FAI under AS9102 is the aerospace format and centres on full characteristic accountability for one part. PPAP is the automotive format and adds process FMEAs, control plans, capability studies and a signed warrant.

### When is a partial or delta FAI allowed?

When a change affects only some characteristics, such as a drawing revision, a new tool or a new process source. The partial FAI covers the affected characteristics, references the earlier full report as its baseline and states the reason.

### Does a first article inspection expire?

Not by date alone, but a break in production does reset it. Supplier procedures based on AS9102 require an update after a two-year lapse, and the IAQG's FAQ says a full FAI would normally be required.

### Can a machine shop license its inspection records to AI companies?

Sometimes. Records the shop owns, such as measurement results and process data for its own or unrestricted commercial work, are the candidates. Customer drawings, contract-restricted data and export-controlled technical data are not the shop's to share.

## Sources

- [IAQG: 9102 first article inspection, frequently asked questions (PDF copy hosted by a supplier)](https://endevco.com/contentstore/mktgcontent/endevco/uploads/2019/02/AS9102-frequently-asked-questions1.pdf)
- [Jedco: first article inspection process for suppliers, AS9102 Rev C (PDF, November 2023)](https://jedinc.com/wp-content/uploads/2023/11/TM-50110J-First-Article-Inspection.pdf)
- [GKN Aerospace: AS9102 first article inspection report, common mistakes (PDF)](https://gknaerospace.com/media/mpibej0a/as9102-first-article-inspection-report-common-mistakes.pdf)
- [Federal Acquisition Regulation 9.302: first article testing and approval](https://www.acquisition.gov/far/9.302)
- [22 CFR 120.33: technical data (International Traffic in Arms Regulations)](https://www.ecfr.gov/current/title-22/section-120.33)
- [AIAG: Production Part Approval Process (PPAP) manual, publication page](https://www.aiag.org/training-and-resources/manuals/details/PPAP-4)

## Related reading

- [Who Owns CNC Programs and G-Code? Machine Shop Files and AI](https://origindatapartners.com/guides/machine-shop-cnc-cam-files-ai)
- [License Manufacturing Quality Records to AI Companies](https://origindatapartners.com/guides/license-manufacturing-quality-records-ai)
- [PPAP in Manufacturing: 18 Elements, Levels and the PSW](https://origindatapartners.com/guides/ppap-in-manufacturing)
- [ITAR and EAR Checklist Before You Share CAD Files With AI](https://origindatapartners.com/guides/itar-ear-checklist-cad-data-ai)
- [Who Owns Contract Manufacturer Tooling and Process Data?](https://origindatapartners.com/guides/contract-manufacturer-design-data-ai)
- [PFMEA: Template, Worked Example and the Control Plan Link](https://origindatapartners.com/guides/pfmea-template)